[Board-2018] Up Date on Dumpster Enclosure
Arthur Dionne
adjd at aol.com
Sat Sep 8 13:34:38 MDT 2018
I think the answer is yes as long as it can be done before Docks Out!
Art
-----Original Message-----
From: Dan Gingras <dgingras at comcast.net>
To: 'Board of Directors' <board at portsmouthyc.org>
Sent: Fri, Sep 7, 2018 9:44 pm
Subject: Re: [Board-2018] Up Date on Dumpster Enclosure
Do we really think we should do this before we ask for a $120 raise in dues?
Dan
From: Board <board-bounces at portsmouthyc.org> On Behalf Of Glenn Michael
Sent: Friday, September 07, 2018 8:36 PM
To: Board of Directors <board at portsmouthyc.org>
Subject: Re: [Board-2018] Up Date on Dumpster Enclosure
Agenda item for meeting next week.
G
On Fri, Sep 7, 2018 at 1:26 PM Wes Smith <wsmith5125 at comcast.net> wrote:
Hi All,
Update on the status of the Dumpster Enclosure.
The Town of New Castle HDC approved our application for construction of the dumpster enclosure. The building permit will be issued today, we have one year to complete installation...
I spoke to 125 Fence regarding purchase and installation. We are looking at approximately 6 weeks. Materials are 4+ weeks from the manufacture. An exact date will be provided once a 50% deposit and signed order is received.
If we want the enclosure installed before Docks Out October 27th we need to act immediately.
What is your pleasure?
Thanks,
Wes Smith
RearComoodre at PortsmouthYC.org
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://portsmouthyc.org/pipermail/board_portsmouthyc.org/attachments/20180908/9b6fac7b/attachment.htm>
More information about the Board
mailing list